Fit-out drawing change log
Use one row per change at the first coordination meeting. The purpose is to leave the meeting knowing who will check each item and which drawing records the answer. Copy the blank row before filling it in.
| Room and proposed change | Drawing and revision reviewed | Question still open | Person to check | Evidence needed to close |
|---|---|---|---|---|
| [Room / change] | [Drawing ID, revision, date] | [One question] | [Name or role] | [Marked-up drawing, written response or survey reference] |
Worked example
A tenant wants to move a pantry sink to the opposite wall. The proposed layout shows the new position. The existing drainage route is missing from the drawing pack. Record those as two separate facts.
| Room and proposed change | Drawing and revision reviewed | Question still open | Person to check | Evidence needed to close |
|---|---|---|---|---|
| Pantry / relocate sink | Proposed layout A-102, Rev B (illustrative) | Where is the existing drainage connection shown? | Building-services coordinator | Reference to the current services drawing or a dated site record confirming the connection |
Closing a row
- Record the source and date of the answer so another team member can find it.
- If the source is inconclusive, leave the row open and name the next person to check it.
- When a drawing is revised, enter the new revision and keep the earlier reference in the change history.
This example is fictional. Use the log to coordinate information. Confirm project-specific design and submission requirements with the responsible project team. For examples of layout changes that can affect building-services drawings, see EMARC’s guide to MEP drawings for Dubai fit-outs.